ANDE president Miguel Báez presented to the Bicameral Committee a draft that allocates USD 956 million to energy purchases and USD 614 million to physical investment. Planned works include the second 500 kV Margen Derecha–Villa Hayes circuit and the 220 kV line to Loma Plata, with a substation in Pozo Colorado. This is a draft budget subject to legislative approval; it does not mean the works are completed or have commissioning dates.